How to Tile a Shower Wall — Step-by-Step UK Guide
Complete guide to tiling a shower wall in the UK, from tanking and backer board through to tile layout, adhesive application and silicone finishing.
What You'll Need
Tools
- Manual or electric tile cutter
- Diamond hole cutter (for mixer/shower valve holes)
- Notched trowel (6mm or 10mm)
- Spirit level (600mm and 1200mm)
- Tile spacers (2mm or 3mm)
- Grout float and sponge
- Silicone gun and smoothing tool
- Drill/driver for backer board fixing
- Tape measure, pencil and straight edge
- Safety goggles, dust mask and gloves
Materials
- Wall tiles (allow 10-15% extra for cuts and waste)
- Tile backer board (12.5mm cement board)
- Backer board screws and adhesive
- Liquid tanking membrane
- Tanking tape and pipe collars
- Flexible waterproof tile adhesive (C2 TE S1)
- Waterproof grout
- Sanitary silicone sealant (mould-resistant)
- Tile trim for exposed edges
Before You Start
- Turn off the water supply if you are working around exposed pipework or replacing a shower valve.
- Strip back to the studs or solid wall. Remove all old tiles, adhesive and damaged plasterboard.
- Check that timber studs are straight and true — pack out any low spots with plywood shims so the backer board sits flat.
- Use our Wall Tile Calculator to work out the number of tiles needed and plan your layout.
- Ensure the shower tray is level and correctly installed before tiling the walls — tiles should overlap the tray upstand.
Step-by-Step Instructions
Step 1: Fix Backer Board
Cut cement backer board to size using a score-and-snap knife or a jigsaw with a masonry blade. Apply flexible adhesive to the studs, then fix the board with backer board screws at 300mm centres. Stagger joints and leave a 3mm gap between boards — fill gaps with flexible adhesive and embed mesh tape.
Step 2: Tank the Shower Area
Apply the first coat of liquid tanking membrane over the entire shower area with a brush or roller. Bed tanking tape into all internal corners, board joints and around pipe penetrations while the first coat is still wet. Allow to dry (2-4 hours), then apply the second coat. Extend the membrane at least 300mm beyond where the shower screen will sit. Use our Wet Room Tanking Calculator to estimate membrane quantities.
Step 3: Plan Your Tile Layout
Dry-lay a row of tiles to plan the layout. Centre the tiles on the back wall of the shower so cuts are equal at each side. Mark a horizontal datum line at the height of one full tile above the shower tray. The bottom row will be cut to fit and tiled last.
Step 4: Fix a Temporary Batten
Screw a straight timber batten along your datum line to support the first row of tiles. This ensures a perfectly level start. You will remove it once the adhesive has cured.
Step 5: Apply Adhesive and Set Tiles
Spread flexible tile adhesive onto the backer board using a notched trowel — work in areas of about 0.5m² at a time. For tiles larger than 300×300mm, also back-butter the tile to ensure full adhesive coverage. Press each tile into the adhesive with a slight twist and insert spacers. Check levels frequently.
Step 6: Cut and Fit Around Pipework
Use a diamond hole cutter on a drill at low speed with water lubrication for pipe holes. Mark the hole position carefully by measuring from adjacent tiles. For the shower valve, you may need a larger hole cutter (50-65mm). Cut L-shapes by scoring with a tile cutter and nibbling with nippers.
Step 7: Tile the Bottom Row
After 24 hours, remove the batten and tile the bottom row. Cut tiles to fit, leaving a 3-5mm gap above the shower tray for silicone. This gap allows for movement and provides a waterproof seal.
Step 8: Grout
Mix waterproof grout and apply with a grout float at 45° to the tile surface. Press firmly into all joints, working diagonally. Wipe off excess with a damp sponge after 15-20 minutes. Do not grout internal corners or the tile-to-tray joint — these are silicone joints.
Step 9: Apply Silicone
After the grout has cured for 24 hours, apply mould-resistant sanitary silicone to all internal corners, the tile-to-tray joint and around pipe penetrations. Use masking tape for clean lines and smooth with a finishing tool. Remove tape immediately.
Step 10: Final Checks
Inspect all joints for gaps. Polish grout haze off tiles with a dry cloth. Refit the shower screen, valve covers and any accessories. Allow silicone to cure for 24 hours before using the shower.
Common Mistakes to Avoid
- Using standard plasterboard: It will absorb moisture and fail within months. Always use cement backer board in shower areas.
- Incomplete tanking: The tanking membrane must be continuous with no gaps. Pay special attention to corners, joints and pipe penetrations.
- Voids behind tiles: Air pockets behind tiles in a shower area will harbour moisture and eventually cause tiles to blow off. Back-butter large tiles for 100% coverage.
- Grouting movement joints: Internal corners and the tile-to-tray joint must be silicone. Grout will crack.
- Not allowing cure time: Rushing to use the shower before adhesive and silicone have fully cured causes early failure.
Cost Estimate (2026 UK Prices)
| Item | Typical Cost |
|---|---|
| Ceramic wall tiles (per m²) | £12-£30 |
| Porcelain wall tiles (per m²) | £25-£60 |
| Tile backer board (per sheet) | £15-£30 |
| Tanking kit (5m² coverage) | £30-£50 |
| Flexible tile adhesive (20kg bag) | £18-£28 |
| Waterproof grout (5kg bag) | £10-£18 |
| Sanitary silicone (per tube) | £5-£10 |
| Total for a shower enclosure (DIY, ~5m²) | £250-£550 |
Use our Wall Tile Calculator and Wet Room Tanking Calculator for exact quantities for your project.
How We Calculate This
Frequently Asked Questions
Related Calculators
How to Apply a Skim Coat
Step-by-step guide to applying a skim coat of plaster to walls and ceilings.
How to Bleed Radiators
Step-by-step guide to bleeding radiators, identifying air locks and repressurising your boiler.
How to Build a Brick Wall
Step-by-step guide to building a brick wall including foundations, bonding and pointing.
How to Build a Garden Wall
Step-by-step guide to building a garden wall with footings, blockwork and coping.
Last updated: April 2026
All calculations are estimates. Verify with your supplier.
