Job Completion Calculator
Estimate how long a trade job will take based on scope and conditions
Diminishing returns: 2 workers ≈ 41% faster, 3 ≈ 58% faster - a rough guide, not a guarantee.
Next up: related pages
How We Calculate This
Frequently Asked Questions
Base durations represent typical jobs in standard conditions. Actual times vary with property age, access difficulty, specification level, and unforeseen issues. Always add contingency - experienced tradespeople typically add 15-25% to their estimates.
Adding workers does not halve the time, because of coordination overhead, sequencing constraints, and shared workspace limitations. As an illustrative rule of thumb, this calculator assumes a second worker saves roughly 40% of the single-worker time and a third saves less again. This is a modelling guide rather than a guaranteed productivity figure — no British Standard governs crew speed, so treat it as indicative and adjust for your own trade and site.
Yes, for regulated work. Building control inspections can add 1-3 days per visit (typically 4-6 visits for an extension). Electrical Part P notifications need inspection before energising. Gas Safe registrations need completing before handover.
For external work (roofing, brickwork, rendering), expect 1-2 lost days per week in winter months. Concrete and mortar cannot be laid in freezing conditions. External decorating needs dry weather. Budget more contingency for autumn/winter starts.
Select "Custom Duration" and enter your own base estimate in working days. The calculator will still apply scope, worker, and delay adjustments to give you a more realistic completion estimate.
Was this calculator helpful?
Last updated: March 2026
Verified against UK standards · estimates only, confirm with your supplier.