Groundwork Excavation Calculator — Volume, Swell & Lorry Loads

Calculate cut volume, swell factor by soil type, lorry loads and disposal costs for groundwork excavation.

Average depth of excavation

How We Calculate This

This calculator determines the cut volume, swelled volume, lorry loads and costs for groundwork excavation.

Volume and swell

Cut Volume = Length × Width × Depth
Swelled Volume = Cut Volume × Swell Factor
Typical swell factors: topsoil 1.25, clay 1.3, sand/gravel 1.15, chalk 1.4, rock 1.5. Bulking is variable (moisture, dig method) — verify for your site material.

Lorry loads

Loads are limited by EITHER volume OR weight, whichever fills the lorry first:
Loads = the greater of ceil(Swelled Volume ÷ Volume Capacity) and ceil(Tonnage ÷ Weight Capacity)
Capacities: 8-wheeler ~8 m³ / 20 t, 6-wheeler ~6 m³ / 16 t, artic ~12 m³ / 29 t. Tonnage = Cut Volume × in-ground density (clay ~1.9 t/m³, rock ~2.2 t/m³).