Strip-Out Calculator
Calculate waste volumes, skip counts, and labour hours for room-by-room strip-out work including plaster, flooring, and fixture removal.
Total wall + ceiling area to strip per room
Floor area to strip per room
Radiators, doors, built-in units etc. (rough allowance: ~35 kg + 0.15 m³ skip space each)
Rooms of similar size to strip out
Typical: 12-15mm gypsum, 20-25mm lime
Total depth including screed and finish
Your labourer hourly rate
Next up: related pages
How We Calculate This
This calculator estimates waste volumes and labour requirements for interior strip-out work on a room-by-room basis. It covers the three main strip-out elements: plaster removal, flooring removal, and fixture removal.
Calculation method
Plaster waste: Wall/ceiling area × plaster depth (typically 12-20mm) gives volume in m³. Plaster density is approximately 1.6 t/m³.
Flooring waste: Floor area × buildup depth (screed + floor finish, typically 20-50mm) gives volume. Weight depends on the buildup: lightweight finishes (timber/laminate/vinyl) ~0.7 t/m³, mixed materials ~1.2 t/m³, and tile or finish over sand-cement screed ~1.9 t/m³ (screed in situ is roughly 1.8-2.0 t/m³). Pick the "Flooring Type" that matches your buildup — the weight estimate will be low if you leave it on "mixed" for a screed-heavy floor.
Fixtures: Each fixture (radiator, door, window frame, built-in unit) is given a rough allowance of about 0.15 m³ of skip space for sizing the skip, and roughly 35 kg for the weight estimate (a typical wall radiator is ~15-35 kg and an internal door ~14-36 kg). Cast-iron radiators and heavy built-ins weigh considerably more, so treat these as ballpark figures, not precise weights.
Labour: Plaster removal ~0.15 hours/m², flooring ~0.1 hours/m², fixtures ~0.5 hours each. These are typical soft-strip productivity allowances used in UK estimating (e.g. SPON's / Wessex-style price books and contractor experience) — they are rules of thumb, not a published standard. Allow more for lime plaster, awkward access or asbestos-managed work.
Frequently Asked Questions
A single room strip-out (removing plaster, flooring, and fixtures) typically takes 1-2 days for a skilled labourer. A full house strip-out of a 3-bed semi can take a 2-person team 5-8 days. Factors affecting speed include plaster type (lime plaster takes longer than gypsum), flooring buildup, and number of fixtures.
A typical 4m x 3m room with plaster removal from all walls and ceiling, plus flooring, generates around 1.5-2.5 m³ of waste (approximately 2-4 tonnes depending on materials). Lath-and-plaster is significantly heavier and bulkier than plasterboard.
Essential PPE includes an FFP3 dust mask (or powered respirator for extended work), safety goggles, steel-toe boots, hard hat, heavy-duty gloves, and hearing protection when using power tools. If asbestos is suspected, work must stop and a survey carried out before continuing.
Yes, under the Waste (England and Wales) Regulations, you should segregate waste where practical. Plasterboard must be kept separate from general waste as it cannot go to mixed landfill. Metals, timber, and plastics should be separated for recycling. Some skip companies offer discounts for pre-sorted waste.
No, load-bearing walls require structural engineering input and Building Control approval before removal. This calculator covers non-structural strip-out (plaster, finishes, fixtures). For wall removal, use our Wall Removal Calculator which accounts for temporary supports and RSJ sizing.