Kitchen Strip-Out Calculator

Calculate waste volumes, labour hours, and skip requirements for a complete kitchen strip-out including units, worktops, tiling, electrical, and plumbing.

How We Calculate This

This calculator estimates waste volumes and labour requirements for a complete kitchen strip-out. It breaks down the work into individual elements for accurate planning.

Waste estimation

Units: Each kitchen unit (base or wall) produces approximately 0.12 m³ of waste when dismantled. Modern MDF/chipboard units are relatively light.

Worktops: Volume calculated as length × 600mm depth × 40mm thickness. Stone worktops are significantly heavier than laminate.

Tiling: Area × 12mm average tile and adhesive depth gives volume. Ceramic tiles have a density of approximately 2.0 t/m³.

Labour rates

Based on RICS industry rates: 0.4 hrs per unit, 0.3 hrs per metre of worktop, 0.15 hrs/m² for tiling removal, 0.5 hrs per electrical disconnection, and 0.75 hrs per plumbing cap-off.

Frequently Asked Questions

Last updated: March 2026

All calculations are estimates. Verify with your supplier.